Completed Projects: 1998, 1999, 2000, 2002, 2003


PROJECTS CURRENTLY UNDER CONSTRUCTION:

DESIGN/BUILD - JAMES E. ANDERSON PARK, LAKEHILLS, TEXAS
Owner: San Antonio Police Benevolent Fund
Contact: Mr. Bill Grayson
Architect: Bartholomew & Company
Contact: Randy Bartholomew 210-826-2911
Contract Amount: $317,488
Percent Complete: 5%

NEW VEHICLE MAINTENANCE BUILDING, CITY OF LIVE OAK, LIVE OAK, TEXAS
Owner: City of Live Oak
Contact: Mark Wagster 210-653-1940 #221
Architect: J. Mendenhall Architects
Contact: Jerry Mendenhall 210-349-2715
Contract Amount: $276,750

JEWEL WEITZEL CENTER - CANOPY ADDITION, HARLANDALE INDEPENDENT SCHOOL DISTRICT, SAN ANTONIO, TEXAS
Owner: Harlandale Independent School District
Contact: Oscar A. Perez 210-921-4335
Architect: Callins Watts Sendejo, Architects
Contact: Robert Watts, Principal 210-824-1435
Contract Amount: $65,800
Percent Complete: 95%

NEW TENNIS COURTS WITH LIGHTING AT NORTHSIDE TENNIS CENTER, NORTHSIDE INDEPENDENT SCHOOL DISTRICT, SAN ANTONIO, TEXAS
Owner: Northside Independent School District
Contact: Henry Acosta 210-257-1232
Engineer: Civil Engineering Consultants
Contact: Jesse F. Cantu 210-641-9999
Contract Amount: $536,250
Percent Complete: 35%

D’HANIS I.S.D. GYMNASIUM, D’HANIS INDEPENDENT SCHOOL DISTRICT, D’HANIS, TEXAS
Owner: D’Hanis Independent School District
Contact: Bruce Davis 830-363-7216
Architect: Fromberg Associates, Inc.
Contact: Matthew Agee 512-495-9171
Contract Amount: $1,500,900
Percent Complete: 65%

CULEBRA TRANSPORTATION STATION PHASE 1B, SAN ANTONIO, TEXAS, NORTHSIDE INDEPENDENT SCHOOL DISTRICT
Owner: Northside Independent School District
Contact: Carlos Alexander 210-257-1207
Architect: Callins Watts Sendejo, Architects
Contact: Robert Watts, Principal 210-824-1435
Contract Amount: $814,750.00
Percent Complete: 95%

PROJECTS COMPLETED IN THE LAST THREE (3) YEARS
2003 COMPLETED PROJECTS
back to top

STORM DAMAGE REPAIR WORK FOR RICK TAYLOR RECREATION CENTER, CITY OF HONDO, HONDO, TEXAS 78861

Owner: City of Hondo
Contact: John Vidaurri, City Manager 830-426-3378
Architect: Barbutti and Associates
Contact: Ronald V. Barbutti, R.A., C.S.I. 830-426-2200
Contract Amount: $171,500.00
Completed: March 7, 2003

TRANSPORTATION SOUTH SATELLITE, PHASE I, RFCSP: 2002-062, SAN ANTONIO, TEXAS, NORTHSIDE INDEPENDENT SCHOOL DISTRICT

Owner: Northside Independent School District
Contact: Carlos Alexander 210-257-1207
Architect: Callins Watts Sendejo, Architects
Contact: Robert Watts, Principal 210-824-1435
Contract Amount: $842,750.00
Completed: March 26, 2003

ADDITIONS AND RENOVATIONS TO WINDCREST CIVIC CENTER, WINDCREST, TEXAS
Owner: City of Windcrest
Contact: Byron Vick 210-655-0022
Architect: j. Mendenhall, Architects
Contact: Jerry Mendenhall 210-349-2651
Contract Amount: $390,250
Completed: May 15, 2003

2002 COMPLETED PROJECTS
back to top

MODIFICATIONS AND ADDITIONS TO LITTLETON GYMNASIUM AT BLOSSOM ATHLETIC CENTER, 12001 JONES-MALTSBERGER, SAN ANTONIO, TEXAS, NORTH EAST I.S.D.
Owner: North East Independent School District
Contact: Garret Sullivan 210-804-7270
Architect: Rehler Vaughn & Koone, Inc.
Contact: Liam Stagg, Associate 210-733-3535
Contract Amount: $2,304,704
Completed: September 27, 2002

SOUTHSIDE MIDDLE SCHOOL, 19190 HWY 281 SOUTH: KITCHEN, CAFETERIA & GYMNASIUM
ADDITIONS, SOUTHSIDE INDEPENDENT SCHOOL DISTRICT, SAN ANTONIO, TEXAS
Owner: Southside Independent School District
Contact: James Carrillo 210-626-0600
Architect: Debra J. Dockery, Architect, P.C.
Contact: Debra Dockery, 210-225-6130
Contract Amount: $ 3,770,400
Complete: July 15, 2002

MILLER ELEMENTARY SCHOOL, 207 LINCOLNSHIRE: ADDITIONS AND RENOVATIONS,
SAN ANTONIO INDEPENDENT SCHOOL DISTRICT, SAN ANTONIO, TEXAS
Owner: San Antonio Independent School District
Contact: Kamal ElHabr, P.E. 210-271-3322
Architect: O’Neill, Conrad, Oppelt Architects, Inc.
Contact: Carlos Constantino 210-829-1737
Contract Amount: $ 2,872,500
Complete: May 30, 2002

H.E.B. INFORMATION SYSTEMS EXPANSION, 4710 N. PAN AM EXPRESSWAY,
SAN ANTONIO, TEXAS
Owner: HEB Grocery Company, LP
Contact: Raymond Howton 210-938-5557
Architect: Kell Munoz Architects
Contact: Richard Slavin 210-349-1163
Contract Amount: $463,550
Complete: June 30, 2002

bITCHEN ADDITIONS AND RENOVATIONS FOR BOONE, CARLOS COON, AND LINTON ELEMENTARY SCHOOLS - RFCSP No. 2001-033Owner: Northside Independent School District
Contact: Carlos Alexander 210-257-1207
Architect: Rehler, Vaughn & Koone
Contact: Hayden Phillips 210-733-3535
Contract Amount: $1,855,481
Complete: June 30, 2002

2000 COMPLETED PROJECTS
back to top

ADDITIONS AND RENOVATIONS TO MADISON ELEMENTARY SCHOOL,
SAN ANTONIO INDEPENDENT SCHOOL DISTRICT, SAN ANTONIO, TEXAS
Owner: San Antonio Independent School District
Contact: Robert Chavez/Tom Curiel 210-271-3322
Architect: Kell Munoz Architects
Contact: Ben Polindo/Richard Slavin 210-349-1163
Contract: $ 3,543,445
Completion Date: August 30, 2000

RENOVATION CENTRAL OFFICE BUILDING “B”, NORTHSIDE
INDEPENDENT SCHOOL DISTRICT, SAN ANTONIO, TEXAS
Owner: Northside Independent School District
Contact: Jim Martin 210-257-1215
Architect: Molina Architects
Contact: Paul Molina 210-340-8082
Contract Amount: $ 712,500
Completion Date: December 15, 2000

ADDITIONS AND RENOVATIONS TO CENIZO PARK ELEMENTARY SCHOOL, EDGEWOOD INDEPENDENT SCHOOL DISTRICT, SAN ANTONIO, TEXAS
Owner: Edgewood Independent School District
Contact: Coy Ballard, Jasmine Construction Management 210-227-3000
Architect: Molina Architects, Inc.
Contact: Paul Molina, Architect 210-340-8082
Contract Amount: $ 774,038.00
Completion Date: August 30, 2000

PRACTICE GYMNASIUM AT CANYON MIDDLE SCHOOL, COMAL INDEPENDENT SCHOOL DISTRICT, NEW BRAUNFELS, TEXAS
Owner: Comal Independent School District
Contact: Guillermo Nieri 830-625-8081
Architect: Reynolds-Schlattner-Chetter-Roll
Contact: Richard Roll 210-340-7973
Contract Amount: $457,500
Completion Date: May 31, 2000

MADISON ELEMENTARY SCHOOL PHYSICAL EDUCATION FACILITY, SAN ANTONIO INDEPENDENT SCHOOL DISTRICT, SAN ANTONIO, TEXAS
Owner: San Antonio Independent School District
Contact: Robert Chavez/Tom Curiel 210-271-3322
Architect: Garza/Bomberger & Associates
Contact: Scott Hanson 210-349-7000
Contract: $ 475,000
Completion Date: March - 2000

PHYSICAL EDUCATION FACILITY PACKAGE “C”, SAN ANTONIO, TEXAS
Owner: San Antonio Independent School District
Contact: Robert Chavez/Tom Curiel 210-271-3322
Architect: Garza/Bomberger
Contact: Scott Hanson 210-349-7000
Contract Amount: $ 2,750,926
Completion Date: February 21, 2000

RENOVATIONS AND ADDITIONS TO PUBLIC SAFETY COMMUNICATION CENTER, SAN ANTONIO, TEXAS
Owner: City of San Antonio
Contact: Chester Slimp 210-207-2155
Architect: Chesney-Morales & Associates, Inc.
Contact: Frank Harrison/Gene Jopling 210-828-9481
Contract: $ 2,540,042
Completion Date: February 15, 2000

1999 COMPLETED PROJECTS
back to top

RICK TAYLOR YOUTH RECREATION CENTER, HONDO, TEXAS
Owner: City of Hondo
Contact: Bill Hall 830-426-3378
Architect: Barbutti & Associates
Contact: Ron Barbutti 830-426-2200
Contract Amount: $ 1,309,150
Completion Date: April 1999

1998 COMPLETED PROJECTS
back to top

ALLIANT TECHNOLOGY SYSTEMS, HANGAR NUMBER 2,HONDO, TEXAS
OWNER: City of Hondo
Contact: Bill Hall 830-426-3378
Contract Amount: $ 290,000
Completed: February 1998


CLINIC ADDITION AND ACCESSIBILITY UPGRADES TO RIDGEVIEW
ELEMENTARY SCHOOL, SAN ANTONIO, TEXAS
Owner: North East Independent School
Contact: Tom Edwards 210-804-7270
Architect: HMG & Associates, Inc. Consulting Engineers
Contact: Angelus Vasquez 210-349-0800
Contract Amount. $ 856,200
Completed: June 1998

HANGAR 9 & 10 RENOVATIONS AT STINSON MUNICIPAL AIRPORT, SAN ANTONIO, TEXAS
Owner: City of San Antonio
Contact: Les Heinen 210-207-3506
Architect: McCall & Associates
Contact: Joe 210-824-8400
Contract Amount: $ 727,750
Completed: July 30, 1998

ADDITIONS & RENOVATIONS TO COLONIAL HILLS ELEMENTARY SCHOOL, SAN ANTONIO, TEXAS
Owner: North East Independent School District
Contact: Tom Edwards 210-804-7270
Architect: Bartholomew & Company, Ltd. Architects
Contact: Randy Bartholomew 210-826-2911
Contract Amount: $ 1,400,000
Completed: December 2, 1999